Wind energy in Colombia: one more year of waiting for it to take off – Sectors – Economy
The Portuguese EDP Renovables, which for several months has been advancing the construction of the first two wind megaprojects in Colombia, received bad news that made it Alpha and Beta power generation starts one year later than planned initially: end of 2024. This is in addition to the blockades that the company has had to face by residents of the area.Although to date Colombia already has three wind farms, these are smaller and together they have a capacity of only 51.5 megawatts, while Alpha and Beta will contribute 492 megawattswhich is equivalent to the electrical energy required to supply a…