After the strong wave of criticism last December and January for the terrible state of the Ruta del Sol, especially in sector 3, The Ministry of Transport committed itself in those days to improve the transitability for transporters and tourists in this holiday season.
As reported by travelers, the road could not fit one more hole and there were many accidents and damage to vehicles caused by lack of maintenance.
“For users whose destination is Bogotá or the North Coast during the holiday season, we have some important advances in the face of the explosions that we are developing by the Invías and the ANI in contracts in execution.”, he assured in a statement from the Ministry of Transportation, in which he reports that Ruta del Sol, sector 3, presents an advance of 55.53 percent.
The project has a total length of 465 kilometers from the municipality of San Roque (Cesar) to the Y of Ciénaga (Magdalena) and from Carmen de Bolívar (Bolívar) to Valledupar (Cesar).
In this section, the Ministry promised to make it passable through the improvement and rehabilitation of the existing road and 465 km of construction of a second carriageway.
(You can read: Massive theft of high-end cars and trucks in a renowned restaurant in Bucaramanga).

Aspect of the Ruta del Sol II when the works were in progress.
Jaime Moreno/EL TIEMPO Archive
The construction of 476 kilometers of dual carriageway is planned, the improvement of 465 kilometers and the operation and maintenance of 941. To date, 307.72 kilometers of new track have been built and 208.84 have been improved, for an advance of 55.5 percent.
According to the current plan, it has been determined that the completion of the works will be on January 26, 2025; therefore, on January 27, 2025, the entire project would enter the operation and maintenance stage.
According to this portfolio, there is to date progress between 50 and 70 percent in trunks 1 and 2 of Magdalena Medio in the preoperative stage, corresponding to a priority intervention.
In the section of Ruta del Sol 1, between Korán and Guaduas there is a breakdown by Invías together with the maintenance crews to improve the conditions affecting mobility.
(Also: Can a turbo be installed in a car that doesn’t come from the factory?).
For the first two trunk contracts (5G) of Magdalena 1 and 2, the start minutes were signed on December 1, 2022.
It began with priority outbreaks such as fissure and crack sealing, patching and patching, subsidence repairs, signaling, removal of landslides, cleaning of banks, ditches and separators, among others, which to date complete an intervention of 203 kilometers of the two corridors. These projects are currently in the preoperative stage.
Because it is the holiday season, there are a greater number of travelers. “This implies responsible behavior, respecting traffic regulations and abiding by the instructions of the authorities on the routes.”, said William Camargo, Minister of Transportation.